4. A takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in:
Useful Links From This Website |
Notifications, Admit Cards, Results, Universities |
Books, Exam Pattern, Mock Tests, Study Materials, Syllabus, Test Papers |
A. 6 days
B. 8 days
C.12 days
D. 4 days